These are examples of the desperate bidding climate for public works projects in the area.

THURSTON COUNTY

 • Independence Road bridge replacement

When: April 2009

Engineer’s estimate: $2,288,000

Winning bid: $1,984,000, 13.2 percent below estimate

 • Oyster Bay Road culvert replacement

When: Late 2009

Engineer’s estimate: $208,000

Winning bid: $185,000, 11 percent below estimate

City of Lacey

 • Gateway wastewater pump station

When: Bid awarded in May 2009

Engineer’s estimate: $7,165,359

Winning bid: $4,828,055, 32.6 percent below estimate

 • Mullen Road extension

When: January

Engineer’s estimate: $4,228,599

Winning bid: $2,790,745, 34 percent below estimate

 • Timberlake neighborhood waterline replacement

When: February

Engineer’s estimate: $399,605

Winning bid: $296,479, 25.8 percent below estimate

City of Olympia

 • First phase of Yauger Park regional stormwater facility expansion

When: January

Engineer’s estimate: $2,863,404

Winning bid: $1,562,424, 45 percent below estimate

 • Second phase of 18th Avenue road improvements

When: March

Engineer’s estimate: $3,406,188

Apparent low bidder*: $2,245,314.57, 34.1 percent below estimate

 • Fourth and Fifth avenue plantings

When: February

Engineer’s estimate: $26,724

Winning bid: $21,737, 18.7 percent below estimate

City of Tumwater

 • Capitol Boulevard repaving from Dennis Street to Israel Road

When: June 2009

Engineer’s estimate: $433,600

Winning bid: $340,131, 21.6 percent below estimate

 • Capitol Boulevard repaving from E to M streets

When: June 2009

Engineer’s estimate: $256,000

Winning bid: $163,633, 36 percent below estimate

 • Water disinfection project

When: October

Engineer’s estimate: $2,094,852

Winning bid: $1,693,696, 19.1 percent below estimate

State of Washington

 • Bike-lane installation and turn-lane improvement under Martin Way I-5 interchange

When: June 2009

Engineer’s estimate: $1,723,066

Winning bid: $1,160,349, 32.7 percent below estimate

 • Tumwater Boulevard I-5 interchange paving and ramp widening

When: June 2009

Engineer’s estimate: $610,224

Winning bid: $500,895, 17.9 percent below estimate

 • First stage of Yelm state Route 510 bypass

When: March

Engineer’s estimate: $8,835,365

Winning bid: $4,146,936, 53 percent below estimate

* Construction contract scheduled to be awarded at the Olympia City Council’s March 16 meeting.

Source: Cities of Lacey, Olympia and Tumwater; Thurston County; Washington State Department of Transportation

Similar stories:

  • Sign of spring: Construction work under way across Olympia

  • Work set to begin on $2.5M project to improve 18th Avenue

  • Tumwater roads gets much-needed attention

  • Overhaul of sagging Stadium Way set to begin by next month

  • Tri-Cities to have 6 times as many liquor sellers

COMMENTS Community Publishing Guidelines

Join the Reader Network

Do you want The Olympian to keep you in mind when we canvass the community for opinions?

Click here and sign up with our Reader Network to offer your view.

_